Campus Network Upgrade
| Project
Name: |
|
Campus
Network Upgrade |
| |
|
|
| Goal: |
|
UCCS
is upgrading all network equipment managed by Information Systems
and Technology (IS&T) located at the downtown and Alpharetta campuses. |
| |
|
|
| Method: |
|
To
provide a solid foundation for a suite of services and applications
as well as to prepare for exciting new technologies on the horizon,
such as: GRID computing, H.323 video conferencing, multicast and IP
Telephony. |
|
|
|
| Schedule: |
|
Initial
estimation of planning, development and implementation: 5 months
Project initiated: June 2005
Proposed roll-out: Fall 2005
Check
Project Status
|
| |
|
|
For
More Info: |
|
Mark Roberson (404) 413-4464 |
|
|
|
Last
Updated: 06/30/05
|
|